Question: Question 1 -- NPV Profiles: Graph the NPV profiles for both projects on a common chart., making sure you identify the crucial points. 0 -$725
Question 1-- NPV Profiles: Graph the NPV profiles for both projects on a common chart., making sure you identify the "crucial" points.
0 -$725 -$850
1 100 200
2 250 200
3 250 200
4 200 200
5 100 200
6 100 200
7 100 200
Note: First column is time, second column is Project A cash flow , third column is Project B flow. This is a two-part question. Answer for first ? is needed to solve ? 2.
Question 2-- IRR Applicability:For what range of possible interest rates would you want to use IRR to choose between the those to projects? For what range would you NOT want to use IRR?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts