Question: Construct the Network Diagram for the Project listed below and identify the critical path and most risky activity. Activity Predecessor Duration (days) 7 B 5

Construct the Network Diagram for the Project listed below and identify the critical path and most risky activity.

Construct the Network Diagram for the Project

Activity Predecessor Duration (days) 7 B 5 C A D D B 6 E C 3 F 4 G DE 8 H F,G 9