Question: QUESTION 1 : Ponds Engineering Company won a new project. They have to perform several activities. Following table and network provides information about the project:

QUESTION 1:
Ponds Engineering Company won a new project. They have to perform several activities. Following table and network provides information about the project:
Normal Crash Normal Crash
Activity Time (days) Time (days) Cost ($) Cost($)
A 755020068900
B 882790027900
C 875630063080
D 985630066460
E 1295630085550
F 141043300112660
G 423950077350
H 542200033460
I 652830041810
J 422340052740
K 11102820037840
L 542350029600
M 652645039950
N 221830018300
O 872000032560
P 421300043490
Q 431210023485
R 643800049660
S 325010062780
T 981790025160
U 1295010081270
V 764510054945
W 873971054425
FOLLOWING NETWORK IS DRAWN WITH NORMAL TIME (DAYS): [DO NOT Include this network in the solution]
(a) How many paths are there in the network?
(b) How many paths in the network started with the activity G?
(c) What is the normal project completion cost?
(d) What is the project completion time?
(e) State critical path/s in the network?
(f) Assume that the project manager wants to shorten the project by five DAYS. What crashing decisions do you recommend meeting the desired completion time? When tie, must prefer least cost.
To answer part #(e) MUST fill out the given table and MUST support your work separately.
Trial Critical
Path/s (Before Crashing) Project
Completion Time (Before Crashing) Activity/
Activities
crashed Crash Cost
1
2
3
4
5

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!