Question: Question 1 The below table shows budgeted cost at completion and actual cost of work performed for two work packages. Using the following data, answer
Question 1
The below table shows budgeted cost at completion and actual cost of work performed for two work packages. Using the following data, answer the following questions:

Work Hours Work Package BCAC ACWP Percent Complete (%) A.00 440 A.10 230 150 56% A.20 210 130 57.9% B.00 645 B. 10 370 75 25% B.20 275 85 28.1%