Question: Question 1 The information for a project is given in the Table below (time in weeks) : Activity Immediate predecessors Activity time (t) A -
Question 1
The information for a project is given in the Table below (time in weeks):
Activity | Immediate predecessors | Activity time (t) |
A | - | 3 |
B | A | 4 |
C | B | 4 |
D | B | 1 |
E | B | 1 |
F | B | 3 |
G | C, D, E, F | 2 |
H | E, F | 1 |
I | G, H | 2 |
J | I | 1 |
Question 2
The information for a project is given in the Table below (time in weeks):
Activity | Immediate predecessors | Activity time (t) |
A | - | 8 |
B | A | 2 |
C | A | 3 |
D | A | 60 |
E | B | 60 |
F | C | 2 |
G | D | 2 |
H | E, F | 20 |
I | G | 10 |
J | H, I | 10 |
K | J | 12 |
L | K | 3 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
