Question: Question 2 The information for a project is given in the Table below (time in weeks): Activity Immediate predecessors Activity time (t) 2 A B

Question 2 The information for a project is given

Question 2 The information for a project is given in the Table below (time in weeks): Activity Immediate predecessors Activity time (t) 2 A B A 6 4 5 D E A B E, D F 2 F 8 G 5 H I A H 4 10 J 3 I GJ K 2 a) Draw a network for this project b) Determine the critical path c) Determine the earliest and latest activity times d) Determine slack time for each activity