Question: Question 1 The risk register contains different sections, such as a unique identifier with the detail required to understand clearly. However, A structured risk statement
Question 1
The risk register contains different sections, such as a unique identifier with the detail required to understand clearly. However, A structured risk statement distinguishes risks from their cause(s) and effect(s). Identify the Potential risk owners is another essential item. Which of the following is the primary responsibility of a risk owner?
| Identify new risks and create workarounds. | ||
| Respond to risk triggers and implemcnt the plnned risk responses. | ||
| Report to the project manager that risk has occurred and note the consequences. | ||
| Quantitatively analyze risks as assigned by the project manager. |