Question: Question 1 Type the critical path using the activity letters in order without spaces, commas, or any other special characters added. For example, typing ABC

Question 1
Type the critical path using the activity letters in order without spaces, commas, or any other special characters added. For example, typing ABC would identify a path from Activity A to Activity B to Activity C. Do not include the words Start or Finish in the identification of the critical path.
ANSWER
Question 2
How long is the critical path in days?
Type your answer using numbers only. Do not type words, commas, decimals, or other symbols (such as $). For example, entering 5 would indicate the critical path is 5 days in duration.
Question 3
Can Activity B be delayed, within limits, without impacting the end date of the project?
Yes
No
Question 4
How many days can Activity B be delayed without delaying the project?
Type your answer using numbers only. Do not type words, commas, decimals, or other symbols (such as $). For example entering 0 would indicate that Activity B can not be delayed. Entering 1 would indicate Activity B can be delayed 1 day.
X days
INSTRUCTIONS Review the information below about our project activities, then answer the four questions that follow. Activity Predecessor Duration (in days) A Start 2 B A 5 A 3 D 2 E C,D 4 E, B 3 Finish F N/A B 5 F 3 Finish E4 Start A 2 C 3 D 2 Key: Activity DurationStep by Step Solution