Question: Question 1 Type the critical path using the activity letters in order without spaces, commas, or any other special characters added. For example, typing ABC

Question 1 Type the critical path using the

Question 1

Type the critical path using the activity letters in order without spaces, commas, or any other special characters added. For example, typing ABC would identify a path from Activity A to Activity B to Activity C. Do not include the words Start or Finish in the identification of the critical path.

ANSWER

Question 2

How long is the critical path in days?

Type your answer using numbers only. Do not type words, commas, decimals, or other symbols (such as $). For example, entering 5 would indicate the critical path is 5 days in duration.

Question 3

Can Activity B be delayed, within limits, without impacting the end date of the project?

Yes

No

Question 4

How many days can Activity B be delayed without delaying the project?

Type your answer using numbers only. Do not type words, commas, decimals, or other symbols (such as $). For example entering 0 would indicate that Activity B can not be delayed. Entering 1 would indicate Activity B can be delayed 1 day.

X days

INSTRUCTIONS Review the information below about our project activities, then answer the four questions that follow. Activity Predecessor Duration (in days) A Start 2 B A 5 A 3 D 2 E C,D 4 E, B 3 Finish F N/A B 5 F 3 Finish E4 Start A 2 C 3 D 2 Key: Activity Duration

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!