Question: Consider the following data to assign elements to workstations in a Line Balancing design. The list of the work elements for the production of the
Consider the following data to assign elements to workstations in a Line Balancing design.
The list of the work elements for the production of the units appears in the table below with the order of precedence and the time they take.

The ideal cycle time is 300 seconds per unit. The ideal minimum number of stations is approximately 3.
a) Draw a precedence diagram and construct a grouping table of elements by station and use them to assign elements to workstations respecting the order of precedence and that the total time of each station does not exceed the ideal cycle time.
Fill in the blanks according to the design achieved:
Item A assigned to workstation number Response Item B assigned to workstation ResponseNumber Item C assigned to workstation number Response Item D assigned to workstation ResponseNumber Item E assigned to workstation ResponseNumber Element F assigned to workstation ResponseNumber Item G assigned to workstation ResponseNumber
b) b) Send the drawing of the precedence diagram and the table of grouping of elements by station station used for the design of part (a). Submit through the area provided at the end of the exam.
Elementos Duracion (segundos) Predecesor(s) A 70 B 60 A 120 B D 60 - E 240 CD F 100 A G 190 E, F Elementos Duracion (segundos) Predecesor(s) A 70 B 60 A 120 B D 60 - E 240 CD F 100 A G 190 E, FStep by Step Solution