Question: QUESTION 1 Using the information below, what is the earliest completion time for this project? Answer with an integer only, no units (ie weeks) Activity

QUESTION 1 Using the information below, what is

QUESTION 1 Using the information below, what is the earliest completion time for this project? Answer with an integer only, no units (ie weeks) Activity Predecessor Time (Weeks) A 8 B A 6 D 9 4 E A 24 F 3 B D,E,F G 3