Question: QUESTION 1 Using the information in Table, assuming that the project team will work a standard working week ( 5 working days in 1 week

QUESTION 1
Using the information in Table, assuming that the project team will work a standard working week (5 working days in 1 week) and that all tasks will start as soon as possible.
(i) Determine the critical path of the project
(ii) Calculate the planned duration of the project in weeks
(iii) Identify any non-critical tasks and the total slack on each
\table[[Activity,Description,Predecessor,Duration],[,,working days],[A,Requirement analysis,None,5],[B,Systems design,A,15],[C,Programming,B,25],[D,Telecoms,B,15],[E,Hardware Installation,B,30],[F,Integration,C,D,10],[G,System testing,E,F,10],[H,Training / Support,G,5],[I,Handover and Go Live,H,5]]
QUESTION 1 Using the information in Table,

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!