Question: QUESTION 1 Using the information in Table, assuming that the project team will work a standard working week ( 5 working days in 1 week
QUESTION
Using the information in Table, assuming that the project team will work a standard working week working days in week and that all tasks will start as soon as possible.
i Determine the critical path of the project
ii Calculate the planned duration of the project in weeks
iii Identify any noncritical tasks and the total slack on each
tableActivityDescription,Predecessor,Durationworking daysARequirement analysis,None,BSystems design,ACProgramming,BDTelecoms,BEHardware Installation,BFIntegration,CDGSystem testing,EFHTraining Support,GIHandover and Go Live,H