Question: Question 10 Select the correct question to the following statement: This is the person responsible for managing the mitigations and contingencies of a risk until
Question 10 Select the correct "question" to the following statement: This is the person responsible for managing the mitigations and contingencies of a risk until it is "resolved" somehow. Group of answer choices A. Who is the project manager? B. Who is the risk resolver? C. Who is the risk identifier? D. Who is the risk mitigator? E. Who is the risk owner?