Question: Question 11 1 pts When calculating earned value, there are several approaches to estimating how complete are tasks that are underway. This approach uses amount
Question 111 pts
When calculating earned value, there are several approaches to estimating how complete are tasks that are underway. This approach uses amount of key input.
Group of answer choices
Critical input use
Proportionality
0-100 percent rule
50-50 rule
Question 121 pts
A project is underway and currently EV=$38,000 and AC=$41,700, PV=$39,100. What is the CPI?
Group of answer choices
0.91
0.94
1.03
1.10
Question 131 pts
The two fundamental objectives of control are the regulation of results and what?
Group of answer choices
Stewardship of organizational assets
Procurement of organizational assets
Refurbishing of organizational assets
Distribution of organizational assets