Question: Question 11 3.33 pts Given the project activity information below, what is the total crash cost if the project manager would like to shorten the

Question 11 3.33 pts Given the project activity

Question 11 3.33 pts Given the project activity information below, what is the total crash cost if the project manager would like to shorten the entire project by three weeks? The activity times shown below are in weeks. Activity Predecessors Normal Minimum Time Crash Cost/Week Time A 8 7 $1500 B A 5 3 $200 2 $300 D A 3 | | E B, C, D 3 F E 2 $250 $300 $500 $750 $975 None of the above