Question: Given the project activity information below, what is the total crash cost if the project manager would like to shorten the entire project by three

Given the project activity information below, what is the total crash cost if the project manager would like to shorten the entire project by three weeks? The activity times shown below are in weeks.

Activity Predecessors Normal Time Minimum Time Crash Cost/Week
A --- 8 7 $1500
B A 5 3 $200
C A 4 2 $300
D A 3 3 ---
E B, C, D 3 3 ---
F E 3 2 $250

$300

$500

$750

$800

$950