Question: Given the project activity information below, what is the total crash cost if the project manager would like to shorten the entire project by three
Given the project activity information below, what is the total crash cost if the project manager would like to shorten the entire project by three weeks? The activity times shown below are in weeks.
| Activity | Predecessors | Normal Time | Minimum Time | Crash Cost/Week |
| A | --- | 8 | 7 | $1500 |
| B | A | 5 | 3 | $225 |
| C | A | 4 | 2 | $325 |
| D | A | 3 | 3 | --- |
| E | B, C, D | 3 | 3 | --- |
| F | E | 3 | 2 | $260 |
Step by Step Solution
There are 3 Steps involved in it
SOLUTION To calculate the total crash cost for shortening the entire project by three weeks we need ... View full answer