Question: Given the project activity information below, what is the total crash cost if the project manager would like to shorten the entire project by three

Given the project activity information below, what is the total crash cost if the project manager would like to shorten the entire project by three weeks? The activity times shown below are in weeks.

ActivityPredecessorsNormal TimeMinimum TimeCrash Cost/Week
A---87$1500
BA53$225
CA42$325
DA33---
EB, C, D33---
FE32$260