Question: QUESTION 11 The table below lists the independent projects that your company is considering to invest: Project Initial investment (USD) NPV (USD) IRR (%) A
QUESTION 11 The table below lists the independent projects that your company is considering to invest: Project Initial investment (USD) NPV (USD) IRR (%) A 290000 65682 13.61 490000 50549 13.68 170000 42534 14.04 D 600000 -51706 11.51 E 160000 41049 13.91 F 510000 75248 13.82 G 380000 109323 14.04 The required return is 12.2 percent. If there is an investment budget ceiling of $1,000,000, what is the total net present value of investment opportunuties missed (the sum of NPVs of the feasible projects that your company couldn't invest) due to budget limit? 93083 116231 50549 125797 108216
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
