Question: Question 13 4 points Save Answer The task Plan Schedule Management is a 4-day task. Expenditures/day are set at $3,000 per day. Day 1 is

Question 13 4 points Save Answer The task "Plan
Question 13 4 points Save Answer The task "Plan Schedule Management is a 4-day task. Expenditures/day are set at $3,000 per day. Day 1 is just completed. Assume the percent complete is 25% and the actual cost is $6,000. What is the cost variance, CV? 50 $3,000 $3,000 $2,000 -$2,000