Question: 14. The task Plan Schedule Management is a 4-day task. Expenditures/day are set at $3,000 per day. Day 1 is just completed. Assume the percent

14.

The task Plan Schedule Management is a 4-day task. Expenditures/day are set at $3,000 per day. Day 1 is just completed. Assume the percent complete is 25% and the actual cost is $6,000. Is the task over, under or on budget? Is the task ahead, behind or on schedule?

a.

Over budget and behind schedule

b.

On budget and ahead of schedule

c.

On budget and behind schedule

d.

Under budget and on schedule

e.

Over budget and on schedule