Question: 14. The task Plan Schedule Management is a 4-day task. Expenditures/day are set at $3,000 per day. Day 1 is just completed. Assume the percent
14.
The task Plan Schedule Management is a 4-day task. Expenditures/day are set at $3,000 per day. Day 1 is just completed. Assume the percent complete is 25% and the actual cost is $6,000. Is the task over, under or on budget? Is the task ahead, behind or on schedule?
| a. | Over budget and behind schedule | |
| b. | On budget and ahead of schedule | |
| c. | On budget and behind schedule | |
| d. | Under budget and on schedule | |
| e. | Over budget and on schedule |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts