Question: Question 14 2 pts Consider the PERT/CPM network below: Finish Start The activity/task times are given in weeks: Task Time A 5 B 3 C

Question 14 2 pts Consider the PERT/CPM network

Question 14 2 pts Consider the PERT/CPM network below: Finish Start The activity/task times are given in weeks: Task Time A 5 B 3 C 7 D 6 E 7 F 3 G 10 H 8 Fill in the blank with the correct answer: The estimated time of completion is weeks. 1