Question: Question 14 (Ch6) For the given activities network, what is the EF value for Activity G? G F 28 28 0 O o 21 7

Question 14 (Ch6) For the given activities
Question 14 (Ch6) For the given activities network, what is the EF value for Activity G? G F 28 28 0 O o 21 7 28 Early Activity Early Start (ES) Name Finish Total Total Float Float Late Start Late Finish Duration LS) LE E 23 17 D 21 5 26 O 0 21 28 4 a. Thirty Two b. Four c. Zero d. None of the given answers