Question: Question 14 (Ch6) For the given Activities network, what is the ES value for activity C? 0 A 2 0 2 8 0 Activity Name

Question 14 (Ch6) For the given Activities
Question 14 (Ch6) For the given Activities network, what is the ES value for activity C? 0 A 2 0 2 8 0 Activity Name Early Finish (EF 0 2 0 2 8 Early Start (ES) Total Float Late Start (LS) Total Float B Duration Late Finish (LF) 0 4 4 4 4 4 a. Two b. Zero c. Eight d. None of the given answers A Moving to another question will save this response