Question: Question 15 1 pts Given below are the following values of a project at a given time PV (Planned Value) = 1000 man/days AC (Actual

Question 15 1 pts Given below are the following
Question 15 1 pts Given below are the following values of a project at a given time PV (Planned Value) = 1000 man/days AC (Actual Cost) = $1500 EV = 1100 man/days . What is the SPI? 1.10 0.666 1.35 .9090