Question: Question 14 1 pts . Given below are the following values of a project at a given time PV (Planned Value) $500,000 AC (Actual Cost)

Question 14 1 pts . Given below are the following
Question 14 1 pts . Given below are the following values of a project at a given time PV (Planned Value) $500,000 AC (Actual Cost) = $600,000 EV = $450,000 . What is the CPI? O 0.75 0.833333 O 1.1111 1.2