Question: Question 15 10 points Save Answer Contract requirements state that a project must be completed within 180 working days, or it will incur penalties
Question 15 10 points Save Answer Contract requirements state that a project must be completed within 180 working days, or it will incur penalties for late completion. Analysis of the activity network reveals an expected project time of 145 working days with a project variance of 400. What is the probability that the project will be completed before the late-payment deadline? Note: Write your answer in whole numbers in percentage (%).
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
