Question: Question 2 1 ( 2 points ) Contract requirements state that a project must be completed within 1 8 0 working days, or it will
Question points
Contract requirements state that a project must be completed within working days, or it will incur penalties for late completion. Analysis of the activity network reveals an estimated project time of working days with a project variance of What is the probability that the project will be completed before the latepayment deadline?
near or almost certain