Question: Question 15 (2 points) In which process does the project manager numerically analyze the combined effect of identified individual project risks and other sources of

Question 15 (2 points) In which process does the
Question 15 (2 points) In which process does the project manager numerically analyze the combined effect of identified individual project risks and other sources of uncertainty on overall project objectives? A) Plan Risk Management B) Identify Risks C) Perform Qualitative Risk Analysis D) Perform Quantitative Risk Analysis