Question: In which process does the project manager numerically analyze the combined effect of identified individual project risks and other sources of uncertainty on overall project
In which process does the project manager numerically analyze the combined effect of identified individual project risks and other sources of uncertainty on overall project objectives?
A. Plan Risk Management B. Identify Risks C. Perform Qualitative Risk Analysis D. Perform Quantitative Risk Analysis