Question: Given the schedule in the following table for a software development project: (12 points) (SO 02) Activity Immediate Duration Early Start Early Finish Late
Given the schedule in the following table for a software development project: (12 points) (SO 02) Activity Immediate Duration Early Start Early Finish Late Start Late Finish Free Total predecessor Date Date Slack Slack Date Date activities 6 01/02/202006/02/2020 A B 7 01/02/2020 07/02/2020 A, B 8. B E B D C. E G A. Draw the Gantt chart of the specified project in the table above? (2 points) B. Complete filling the table if the start date of the project is on Saturday 01/02/2020 (assume no vacations) and calculate the needed dates and values: (10 points) 6. C.
Step by Step Solution
3.49 Rating (146 Votes )
There are 3 Steps involved in it
A The Gantt chart of the above specified table is B Project table ... View full answer