Question: Question 16 (1 point) Saved The following represents a project with known activity times. All times are in weeks. Immediate Time Activity Predecessor weeks) A

Question 16 (1 point) Saved The following
Question 16 (1 point) Saved The following represents a project with known activity times. All times are in weeks. Immediate Time Activity Predecessor weeks) A - 4 B 3 A A N D B 7 E C D 9 F B B 5 What is the minimum possible time required for completing the project (reund it to the mearst whole number? Your Answer: Your