Question: complete every thing in excel The following represents a project with known activity times in weeks. Activity Immediate Predecessor Activity Time (wks) A - 4
complete every thing in excel
- The following represents a project with known activity times in weeks.
| Activity | Immediate Predecessor | Activity Time (wks) |
| A | - | 4 |
| B | A | 3 |
| C | - | 2 |
| D | A | 7 |
| E | C | 3 |
| F | B, E | 5 |
| G | D, E | 4 |
| H | F | 5 |
- Create a CPM Network. (40 pts)
- What activities are on the critical path? (10 pts)
- Compute the slack time for activities B and D. (20 pts)
- What is the earliest finish for C and latest start for E? (20 pts)