Question: Question 16 6.25 points Save Answer The table below lists the independent projects that your company is considering to invest: Project Initial investment (USD) NPV

Question 16 6.25 points Save Answer The table below lists the independent projects that your company is considering to invest: Project Initial investment (USD) NPV (USD) IRR (%) A 270000 58281 10.56 B 230000 63654 11.33 C 570000 82047 10.06 ID 490000 55889 10.16 E 370000 -30078 8.11 F 110000 24391 10.62 G 390000 106572 10.55 The required return is 8.9 percent. If there is an investment budget ceiling of $1,000,000, what is the total net present value of investment opportunuties missed (the sum of NPVs of the feasible projects that your company couldn't invest) due to budget limit? 82047 140328 137936 121935 145701