Question: QUESTION 16 A project quality management plan should describe how to identify all of the following: EXCEPT a. Key project deliverables and processes to be

QUESTION 16

A project quality management plan should describe how to identify all of the following: EXCEPT

a.

Key project deliverables and processes to be reviewed for satisfactory quality level

b.

Quality roles and responsibilities

c.

Plan for process improvement and change control

d.

Quality control and assurance activities