Question 16 Use the crash cost data below to
Question 16 Use the crash cost data below to crash this project by five days. The paths and their beginning lengths are: ACF = 13 ADG = 14 BEG = 15 Activity A B C D E Possible Cost per Crashes Day 1 75 2 40 3 90 50 2 110 T 1 60 2 50 6 What is the cost of the first crash? Previous Next >