Question: Question 17 2 pts Consider the following data: Initiation Planning Analysis Design Implementation Testing Closure # Months 2 6 8 6 18 6 2 estimated

Question 17 2 pts Consider the following data:
Question 17 2 pts Consider the following data: Initiation Planning Analysis Design Implementation Testing Closure # Months 2 6 8 6 18 6 2 estimated to complete Budgeted 2000 6000 12000 12000 80000 36000 4000 Cost $ % work 100% 100% 80% 20% 0% 0% 0% completed Actual Cost $ 4000 8000 16000 20000 We are tracking the amount of work completed after 22 months. For the data given, find the planned value (PV) at the end of 22 months. $ 34000 $ 32000 $ 40000 $ 42000