Question: Question 18 2 pts Consider the following data: CO 02 Initiation Planning Analysis Design Implementation Testing Closure # Months 21 6 8 18 6 2

Question 18 2 pts Consider the following data: CO
Question 18 2 pts Consider the following data: CO 02 Initiation Planning Analysis Design Implementation Testing Closure # Months 21 6 8 18 6 2 estimated to complete Budgeted 2000 6000 12000 12000 80000 36000 4000 Cost $ % work 100% 100% 80% 20% 0% 0% 0% completed Actual Cost $ 40001 8000 16000 20000 We are tracking the amount of work completed after 22 months. For the data given, find the earned value (EV) at the end of 22 months. 17000 $ 18600 $ 20000 $ 22000