Question: Question 18 (10 points) Listen The network below represents a project being analyzed by the critical path method. Activity durations are A = 5, B

Question 18 (10 points) Listen The network below

Question 18 (10 points) Listen The network below represents a project being analyzed by the critical path method. Activity durations are A = 5, B = 2, C = 12, D = 3, E = 5, F = 1, G = 7. H = 2,1 = 10, and J = 6. B H A J B Start 12 D F 10 Calculate the ES.EF, LS,LF and slack for the activities on this network. (6 M 212Mark