Question: Question 18 14 Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J 15 10 8 K 9 8 7

Question 18 14 Consider the network described in
Question 18 14 Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J 15 10 8 K 9 8 7 L J 10 6 5 M J 3 3 3 N K.M 9 5 1 lo KM 10 7 4 P LN 10 3 8 If the project due date is 30 weeks then what is the probability that porject will be complete before or by 30 week? Moving to another question will save this response. MacBook Pro