Question: Question 2 ( 1 point ) Now consider door production for a sedan, i . e . , 1 set contains 4 types of doors;

Question 2(1 point)
Now consider door production for a sedan, i.e.,1 set contains 4 types of doors; 2
min to produce a door. It still takes 50 minutes to configure the machine when
changing type
Flow unit: a set of 4 doors
Capacity [set/hour] and designed cycle time (CT) in [minute/set]:
Keep two decimals if required.
If using a batch size of 25 sets:
Capacity =
A set/hour].
CT=
A ,[minset].
if using a batch size of 100 sets:
Capacity =
A set/hour].
CT=
A/minset.Using the attached table, fill in Blank A, B, C, and D. Keep two decimals if
required.
Blank A:
A
Blank B:
A pair/hour].
Blank C:
A/
Blank D:
A/[pair/hour]. Keep two decimals.
 Question 2(1 point) Now consider door production for a sedan, i.e.,1

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!