Question: Question 2 1.25 points You are preparing a progress report on the construction of a 10,000 sf warehouse building at Month 3 using the
Question 2 1.25 points You are preparing a progress report on the construction of a 10,000 sf warehouse building at Month 3 using the Earned Value Analysis method. The following is the progress schedule to date. What was the percent actual completion (PAC) of the project as of this reporting period? Use the EAC forecast to calculate your PAC. Save Answer Progress Schedule Task Schedule of Values % Planned to % Completed Date to Date Foundation $100,000 100% 100% Structure $750,000 100% 100% Building Envelope $250,000 75% 35% Roof $100,000 0% 0% Finishes $100,000 0% 0% Electrical $100,000 0% 0% Mechanical $100,000 0% 0% Total $1,500,000 62.50% 60.00% 57.50% 65.00%