Question: Question 2 2 ( 1 5 points ) Based on the network diagram below, calculate the earliest start and earliest finish, latest start and latest

Question 22(15 points)
Based on the network diagram below, calculate the earliest start and earliest finish, latest start and latest finish for Activity F, and select the correct answer.
Question 22 options:
a)
Earliest start =43, earliest finish =55, latest start =43, latest finish =55
b)
Earliest start =43, earliest finish =55, latest start =45, latest finish =57
c)
Earliest start =45, earliest finish =57, latest start =45, latest finish =57
d)
Earliest start =45, earliest finish =55, latest start =45, latest finish =55

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!