Question: QUESTION 2 [20 marks] Q2(a). Given the project data and assumptions in Table Q2 below, develop a report containing the following: Activity Immediate Predecessor Duration
![QUESTION 2 [20 marks] Q2(a). Given the project](https://dsd5zvtm8ll6.cloudfront.net/si.experts.images/questions/2024/12/6753e4f1df23a_3456753e4f14747f.jpg)
![QUESTION 2 [20 marks] Q2(a). Given the project](https://dsd5zvtm8ll6.cloudfront.net/si.experts.images/questions/2024/12/6753e4f29dac1_3466753e4f24e2e9.jpg)
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
