Question: QUESTION 2 ( 3 . 0 0 points ) Develop a resource schedule for the project network below. The project involves a which requires a

QUESTION 2(3.00 points)
Develop a resource schedule for the project network below. The project involves a which requires a team of programmers for its development. However, only 5 programmers are available.
Activity Subtitle
\table[[ES,ID,EF],[SLACK,RESOURCE,SLACK],[LS,DURATION,LF]]
Use the parallel method and the following heuristics to develop a schedule for the project: 1. Shortest slack. 2. Shortest duration. 3. Smallest identification number.
a) Present the project's workload. Report eventual resource overallocations. (1.50 point)
b) Present a new workload for the project. What is the new critical path and project duration after rescheduling the resources? (1.50 point)
PLEASE PLUG INTO EXCEL SHEET
ORIGINAL LOAD CHART
\table[[ID,RES.,DUR.,ES,LF,SLACK,0,1,2,3,4,5,6],[,,,,,,,,,,,,],[,,,,,,,-,,,,,],[,,,,,,,,,,,,],[,,,,,,,,,,,,],[,,,,,,,,,,,,],[,,,,.,,,,,,,,],[,,,,,,,,,,,,],[,,,,,,,,,,,,],[,,,,,,,,,,,,],[TOTAL RESOURCES,0,0,0,0,0,0,0],[RESOURCES AVAILABLE,5,5,5,5,5,5,5]]
DURATION:
CRITICAL PATH:
RESCHEDULED LOAD CHART
\table[[ID,RES.,DUR.,ES,LF,SLACK,0,1,2,3,4,5,6
 QUESTION 2(3.00 points) Develop a resource schedule for the project network

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!