Question: Please consider the following Network. LEGEND: ES ID EF TE TE LS Dur LF Lag: Lag Lag 6 The figure above only visualises the

Please consider the following Network. LEGEND: ES ID EF TE TE LS

Please consider the following Network. LEGEND: ES ID EF TE TE LS Dur LF Lag: Lag Lag 6 The figure above only visualises the activities and their relationships in an AON diagram. For details, such as activity durations and lags (for the relationships), please consider also the table below. Hint: You may want to print the network to fill it out by hand. Note that the lags to be entered in the figure are highlighted in bold font in the table below. Please complete the forward pass and the backward pass and fill in the ES, EF, LS and LF values below. Be careful: There is no partial credit for this question. You either get it right or you don't! If you get the forward pass right, you will earn half of the points. Getting the backward pass right will earn you the second half of the points. Aotivity ID Duration Predececcore ES EF LS LF 1. (0) 12 11 13 12 238 14 10 2F8-3, 3 3, 4FF+10 (0) 4FS+8, 5

Step by Step Solution

3.45 Rating (148 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

To solve this problem using the Critical Path Method CPM well first carry out the forward pass to ca... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!