Question: Question 2 (30 Points) Continued from Question 2 The capacity information of Product X is listed below. Regular Capacity 100 unit per month Regular Cost

Question 2 (30 Points) Continued from Question 2
The capacity information of Product X is listed below.
Regular Capacity 100 unit per month
Regular Cost - $1,250 per unit.
OT Capacity 20 unit per month
OT Cost - $1,400 per unit
Subcontract Capacity 30 unit per month
Subcontract Cost - $1650 per unit
Holding Cost - $180 per unit per month
Backlog NOT allowed.
With the above information, establish the Aggregate plan for the following three options.
- Option 1, use regular, OT and subcontract to satisfy all the demand.
- Option 2, use regular, OT and inventory to satisfy all the demand.
Option 3, use regular, OT, subcontractor and inventory to satisfy all the demand
Unmesh Kanswered this 1,773 answers a) Total demand = 670 =100+110+120+140+100+100 = 670 b) Total defectives = 33.5 =(5%*100)+(59*110)+(5%*120)=(5%*140)+(5%*100)+(5%*100) = 33.5 c) New values are as follows: July: 100+(5%*100) = 105 August: 110+(596*110) = 115.5 September: 120+(5%*120) = 126 October: 140+(59*140) = 147 November: 100+(5%*100) = 105 December: 100+(5%*100) = 105Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
