Question: Question 2 4 ( 1 point ) 1 ) ListenWhen a project is scheduled from a Finish date, all tasks are scheduled to begin as

Question 24(1 point)1) ListenWhen a project is scheduled from a Finish date, all tasks are scheduled to begin as early as possible.True) FalseQuestion 25(1 point)ListenTo insert a new task, you can right-click a task ID number, and then clickAdd TaskKey TaskTask ValueInsert Task