Question: QUESTION 2 ( 4 MARKS ) In rifate Four ( 4 ) reasons why project planning is importance in successful execution of projects; QUESTION 3

QUESTION 2(4 MARKS)
In rifate Four (4) reasons why project planning is importance in successful execution of projects;
QUESTION 3(4 MARKS)
Givefl| explain what is involved in Project Control.
QUESTION 4(4 MARKS)
project control is a very important aspect in ensuring project success. What are the four main constraints we should control during project implementation?
QUESTION 5(8 MARKS)
Estmates are very critical in successful execution of projects. Briefly explain the following two approaches nestitating project times and costs.
Top-down estimating (4 marks); and
Bottom-up estimating (4 marks).
QUESTION 6(5 MARKS)
Given an activity of fixing 900m2 of formwork for bridge deck, if one carpenter takes on average 2hrsm2 aculate how long it would take:
One (1) carpenter to complete the works (3marks); and
Six (6) carpenters to complete the works (3 marks).
QUESTION 2(4 MARKS)
Indeate Four (4) reasons why project planning is importance in successful execution of projects;
QUESTION 3(4 MARKS)
Givfl| explain what is involved in Project Control.
QUESTION 4(4 MARKS)
project control is a very important aspect in ensuring project success. What are the four main constraints we should control during project implementation?
QUESTION 5(8 MARKS)
Estmates are very critical in successful execution of projects. Briefly explain the following two approaches nestimating project times and costs.
Top-down estimating (4 marks); and
Bottom-up estimating (4 marks).
QUESTION 6(5 MARKS)
Given an activity of fixing 900m2 of formwork for bridge deck, if one carpenter takes on average 2hrsm2, calulate how long it would take:
One (1) carpenter to complete the works (3marks); and
Six (6) carpenters to complete the works (3 marks).
 QUESTION 2(4 MARKS) In rifate Four (4) reasons why project planning

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!