Question: Question 2 4 o f 4 8 What does not accurately describe the work breakdown structure ( WBS ) / task list? It allows project
Question
What does not accurately describe the work breakdown structure WBStask list?
It allows project deliverables and work to be divided into manageable tasks and subtasks.
It is a list of activities showing the tasks that need to be completed and who will complete the task.
It helps ensure no tasks have been omitted.
It requires sequencing of tasks prior to project scheduling.