Question: Question 2 ( 4 points ) A good starting point for developing time and cost estimates is Past experience. Work packages. Task analysis. Time and

Question 2(4 points)
A good starting point for developing time and cost estimates is
Past experience.
Work packages.
Task analysis.
Time and motion studies.
Work breakdown structure.
 Question 2(4 points) A good starting point for developing time and