Question: Question 2 6 ( 2 points ) Why is determining critical path ( s ) of a project so important for a project manager? Because
Question points
Why is determining critical paths of a project so important for a project manager?
Because it can tell the project manager
a how long will it take to complete a program
b how long will it take to complete an activity
c how long will it take to complete a portfolio
d how long will it take to complete a project
e how long will it take to complete a task